Friday, September 18, 2015

Powder Room update

Inspections are completed or in progress.

Plumbing inspection was on Monday right after the plumbers finished up. The plumbers came back on Wednesday to hook up the radiator. All that has gone smoothly.

Electrical inspection was Tuesday after missed attempt on Monday. The electrical inspector couldn't find the bathroom on his own! I made sure I was here for his second visit.

The framing inspection is going to be by texted photograph. The carpenter came today to put in the small amount of framing that is needed. Jon is coming back this afternoon to take a photo and send to inspector.

Sheetrock will be going up on Monday. I am to do painting on Wednesday. The electrician will come back on Thursday to install the light fixture. The plumbers will also come on Thursday to install the toilet and sink.

The toilet has been in for a while. The actuator is in. The sink has arrived. I picked up the light fixture today. The faucet is to arrive on Monday. I need to get the flooring. I already have the paint.

Looks like this project is going to actually finish up soon. The goal is to have it completed or at least usable by Sunday September 2 for Apple Fest.

No comments: